§ 67.1-4-6. Wastewater Discharge Permit Application Contents.  


Latest version.
  • (a)

    No permit shall be granted to an Industrial User until it has submitted the information required by Section 67.1-6-1 of this ordinance, as applicable, and an application containing the following information:

    (1)

    Description of the activities, facilities, and plant processes on the premises, including a list of all raw materials and chemicals used or stored at the facility which are, or could accidentally or intentionally be, discharged to the POTW.

    (2)

    Number and type of employees, hours of operation, and proposed or actual hours of operation.

    (3)

    Each product produced by type, amount, process or processes, and average rate of production.

    (4)

    Type and amount of raw materials processed (average and maximum per day).

    (5)

    The site plans, floor plans, mechanical and plumbing plans, detailed to show all sewers, floor drains, and appurtenances by size, location, and elevation, and all points of discharge.

    (6)

    Time and duration of discharges.

    (7)

    If additional pretreatment or operation and maintenance ("O&M") will be required to meet the standards, then the Industrial User shall prepare a schedule to indicate the shortest amount of time necessary to accomplish installation or adoption of such additional treatment or O&M and in no event shall the completion date be later than the compliance date established for an applicable pretreatment standard. The following conditions apply to this schedule:

    (A)

    The schedule shall contain dates for the commencement and completion of additional pretreatment measures as required for the Industrial User to meet the applicable pretreatment standards. No increment shall exceed nine months, nor shall the total compliance period exceed 18 months.

    (B)

    No later than 14 days following each date in the schedule and the final date for compliance, the Industrial User shall submit a progress report to the Director including as a minimum, whether or not the Industrial User complied with the requirements for incremental progress, the reason for any delay, and the steps being taken by the Industrial User to return to the established schedule. In no event shall more than nine months elapse between such progress reports to the Director.

    (8)

    Any other information deemed necessary by the Director to evaluate the wastewater discharge permit application.

    (b)

    Incomplete or inaccurate applications will not be processed and will be returned to the Industrial User for revision.

    (c)

    The Director may periodically require Industrial Users to update wastewater discharge permit application information. Failure to provide such information within a reasonable period of time shall be grounds to terminate service to the Industrial User. (44-09-67.1.)